St. Laurent & Son is doing a total parking lot reconstruction, which includes the addition of 81 new parking spaces at the VIP Tire and Service Support Center on Lexington Avenue in Lewiston.
When complete a total of 115 spaces will be available for the employees.
The old asphalt will be excavated and recycled at the St. Laurent & Son gravel pit. The crew will install sub-base to spec and finish off with 4 inches of new pavement.
The crew will also build a retention pond with an outlet control structure and a level lip spreader. This system allows heavy sediment and debris to settle in the retention pond. Any overflow water
exits evenly, filtered by a buffer before entering the eco-system.
The project will be completed by late October 2016.